Cluster One
Project Name/Route | Length(km) | Status |
Abogimile-Eleru Rd | 4.0 | Design Completed |
Agbowu-Idiroko | 3.2 | Design Completed |
Eleke-Kanko | 3.9 | Design Completed |
Akinleye-Idi-Iroko | 3.9 | Design Completed |
Agoro-Ikonifin | 11.0 | Design Completed |
Ikonifin-Sade-Ajagunlase | 13.7 | Design Completed |
Ajagunlase-Bode Osi | 8.4 | Design Completed |
Akinleye-Aba Ayo-Isero | 13.0 | Design Completed |
Patara-Ileko Oba-Omi-Road 1 | 3.5 | Design Completed |
Total | 64.6 |
Cluster Two
Project Name/Route | Length(km) | Status |
Jagun Osin-Osisoko road | 10.5 | Design Completed |
Osi Sooko-Elebu-Ara-Osi | 9.5 | Design Completed |
Ara-Osi-Falala | 9.3 | Design Completed |
Alogba-Owode | 10.9 | Design Completed |
Owode-Oyere Fadehan | 15.9 | Design Completed |
Shasha Forest Road | 53.9 | Design Completed |
Total | 110.0 |
Cluster Three
Project Name/Route | Length(km) | Status |
Ilesa-Araromi Igbowiwi | 11.7 | DesignCompleted |
Jabu-Ikeji-Ira | 10.1 | Design Completed |
Ira-Ajebandele Arinmo | 3.85 | Design Completed |
Oligeri-Iragbiji-Oniyo | 3.2 | Design Completed |
Isale General-Muroko-Okebode | 11.65 | Design Completed |
Total | 54 |
See more information here…
https://www.facebook.com/NigeriaRAMP
http://leadership.ng/nga/articles/22545/2012/04/20/world_bank_afd_contribute_36m_fund_ramp_ii.html
http://news.xinhuanet.com/english/world/2012-04/21/c_131542457.htm